By Jiten Yumnam
In the state of Sikkim, land of rhododendrons, in the Himalayan
foothills in India’s North East, rivers have been aggressively dammed
over the last decades. Dam developers are pushing these projects as
clean energy sources to seek carbon credits as additional profits from
the UN Clean Development Mechanism (CDM). More than fifteen mega hydro
projects are already seeking carbon credits in Sikkim where hydropower
is common practice. Some of these wrong decisions should be reversed and
no further projects must be approved.
The 500 MW Teesta VI project of Lanco Energy Private Limited is a
hydropower project located on the Teesta River at Subin Khor village of
South Sikkim. On the same river, the 1200 MW Teesta III project is one
of India’s largest hydropower projects trying to register under the CDM.
Providing a misleading picture to the UNFCCC to receive undue CDM
benefits, both the Teesta III and the Teesta VI project are clearly not
additional. They are common practice because all power plants in India’s
north-east are hydro power stations. What’s more, neither during
stakeholder consultations nor at public hearings the project developers
did reveal that these projects are planning to seek CDM credits. This
makes the obligatory stakeholder consultation process under the CDM
faulty. Fortunately both project are still at validation and have not
generated carbon credits so far.
The dams in Sikkim are not green and clean and will only worsen
global warming if their credits are used to comply with emission
reduction obligations.
However, the non-recognition of Lepcha peoples’ rights over their
land and their exclusion in decision making processes for dams on their
sacred Teesta River remain key issues. The Lepcha peoples’ wishes, to
protect the sacred Teesta River and their last reserve, the Dzongu, have
been completely dishonoured. The blasting for construction of the
project has led to severe landslides in hills and destruction of several
houses near the dam site. A holistic impact assessment on ecology,
seismic impacts, transmissions lines, impact of reduced flow and other
impacts on Lepcha People such as blasting, is absent from its
Environmental Impact Assessment (EIA).
Other common practice large hydro projects in Sikkim such as the 96
MW Jorethang Loop project of DANS Energy Private Ltd on the Rangit River
are already registered as CDM projects. They are now generating non
additional carbon credits. More projects are knocking the door in the
registration pipeline. Those projects do not reduce emissions compared
to what would happen without the CDM and do not contribute to
sustainable development (to the contrary!). They must therefore be
rejected by the CDM Executive Board.
Conclusions & Recommendations
International and national CDM policy is too weak to govern CDM projects and their impact assessment. There is no credible independent verification of developers’ claims regarding approval criteria. According to a Wikileaks cable, the NCDMA does not actually evaluate projects for sustainable development or additionality. Indeed, experience has shown that the Indian DNA and the UNFCCC approve almost all projects even when credible unchallenged evidence is presented.
International and national CDM policy is too weak to govern CDM projects and their impact assessment. There is no credible independent verification of developers’ claims regarding approval criteria. According to a Wikileaks cable, the NCDMA does not actually evaluate projects for sustainable development or additionality. Indeed, experience has shown that the Indian DNA and the UNFCCC approve almost all projects even when credible unchallenged evidence is presented.
Hydro power plants are common practice in Sikkim and other parts of
India’s North East region and the projects do not rely on carbon credits
to be financial feasible, even more so at the current price of carbon
credits. The dams in Sikkim are not green and clean and will only worsen
global warming if their credits are used to comply with emission
reduction obligations. At the same time they will destroy the backbone
of livelihood support for millions. Most dam projects ignore the
recommendations of the World Commission of Dams (WCD) and the
recommendations of the UN Committee on Elimination of Racial
Discrimination in 2007 to respect indigenous people’s rights in dam
construction in India’s North East. All validation and registration of
big hydro projects for CDM from Sikkim and other parts of India’s North
East should therefore be revoked immediately and no new projects
approved. Indigenous peoples’ rights in Sikkim must be fully recognized
in all development policies and projects.
No comments:
Post a Comment